Correct option is B
Given:
A can complete the work in 14 days.
B can complete the work in 21 days.
B works alone on day 1, A works alone on day 2, and this process continues alternately until the work is completed.
Solution:
Let the total work be the LCM of 14 and 21, which is 42 units.
A's one day work = = 3 units
B's one day work == 2 units
In two days, the work done is 3 + 2 = 5 units.
In 16 days (8 cycles of 2 days), the work done is 5 8 = 40 units.
On the 17th day, B works and does 2 units of work.
Total work done = 40 + 2 = 42 units.
Therefore, the total number of days taken to complete the work is 17 days.