Correct option is B
Given:
6 men complete the work in 10 days.
3 women complete the work in 14 days.
We need to find the time taken if 7 women + 5 men work together.
Formula Used:
Work = Rate × Time
Solution:
Work done by 6 men in 10 days = 1 (whole work).
So, work done by 1 man in 1 day:
Work done by 3 women in 14 days = 1 (whole work).
So, work done by 1 woman in 1 day:
Work done by 5 men in 1 day:
Work done by 7 women in 1 day:
Combined 1 day work =
Total days required =
7 women and 5 men can complete the work in 4 days.
Alternate Method:
Total work = LCM of (60, 42) = 420 units.
1 man’s efficiency = 420 ÷ 60 = 7 units/day.
1 woman’s efficiency = 420 ÷ 42 = 10 units/day.
5 men’s efficiency = 5 × 7 = 35 units/day.
7 women’s efficiency = 7 × 10 = 70 units/day.
Combined efficiency = 35 + 70 = 105 units/day.
Days = 420 ÷ 105 = 4 days.