A can do a work in 9 days and B in 12 days. They work on alternate days, beginning with B. In how many days will the work be completed?
Answer & Solution
Correct option is C
Given
Time taken by A = 9 days
Time taken by B = 12 days
They work on alternate days starting with B.
Formula Used
Total Work = LCM of times taken
Efficiency =
Solution
Let the total work be the LCM of 9 and 12, which is 36 units.
Efficiency of A = units/day
Efficiency of B = units/day
In a 2-day cycle (B on day 1, A on day 2):
Work done = 3 + 4 = 7 units
In 5 such cycles (10 days):
Work done = 5 × 7 = 35 units
Remaining work = 36 - 35 = 1 unit
On the 11th day, it is B's turn.
Time taken by B to finish the remaining 1 unit = day
Total time taken = days
Final Answer
So the correct answer is (c)