Which of the following is not a component of project life cycle?
Question

Which of the following is not a component of project life cycle?

A.

Conception

B.

Preparation

C.

Appraisal

D.

Awareness

Correct option is D

✅ (d) Awareness: • Awareness is not a formal phase in the project life cycle. • Key components of the project life cycle include:
· Conception (idea generation)
· Preparation (feasibility and planning)
· Appraisal (evaluation of economic, financial viability)
· Implementation and monitoring • Awareness is part of communication but not a project phase.

Free Tests

Free
Must Attempt

IBPS Agriculture Field Officer (Mains) Mock 02

languageIcon English
  • pdpQsnIcon60 Questions
  • pdpsheetsIcon60 Marks
  • timerIcon45 Mins
languageIcon English
Free
Must Attempt

UPSSSC AGTA PYP Held on July 13, 2025

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon120 Mins
languageIcon English
Free
Must Attempt

UPSSSC AG TA Full Length Mock 01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon120 Mins
languageIcon English
test-prime-package

Access ‘UPSSSC AG TA’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
446k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow