Correct option is B
Let the total work be represented by 1 unit of work.
- V can complete the work in 10 days. Therefore, V’s rate of work is:
Rate of V = 1/10 units per day.
- W can complete the work in 15 days. Therefore, W’s rate of work is:
Rate of W = 1/15 units per day.
Now, they are hired to complete the work in 4 days. Let Z’s rate of work be r_z, where r_z is the amount of work Z completes per day.
The total amount of work done by V, W, and Z in 4 days must equal the total work (1 unit):
First, calculate the combined rate of V and W:
First, calculate the combined rate of V and W:
Now, substitute this into the equation:
Solve for r_z:
Thus, Z’s rate of work is 1/60 units per day. Since Z works for 4 days, the total work done by Z is:
Work done by
Therefore, Z's earnings are proportional to the work done by Z:
Z's earnings = (1/3) x 900 = Rs 300