The variable cost is a component of total cost; another is ________. I. Marginal cost II. Fixed cost III. Average cost
Question

The variable cost is a component of total cost; another is ________.
I. Marginal cost
II. Fixed cost
III. Average cost

A.

only I

B.

Only II

C.

Only III

D.

All I, II, And III

Correct option is B


The variable cost is a component of total cost, another is fixed cost

Free Tests

Free
Must Attempt

Fundamentals of Food Safety: Definitions, Additives & Contaminants

languageIcon English
  • pdpQsnIcon30 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon27 Mins
languageIcon English
Free
Must Attempt

UPSSSC Cane Supervisor Full Length Mock 01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon120 Mins
languageIcon English
Free
Must Attempt

CUET PG Agribusiness Management (ABM) Full Mock Test : 01

languageIcon English
  • pdpQsnIcon75 Questions
  • pdpsheetsIcon300 Marks
  • timerIcon90 Mins
languageIcon English
test-prime-package

Access ‘MP RAEO/RHEO/SADO’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow