Correct option is A
Given:
P and Q can do the job in 90 days.
Q and R can do the job in 112.5 days.
P and R can do the job in 150 days.
X is 5 times as efficient as P.
Y is as efficient as Q.
Z is 2.5 times as efficient as R.
Formula Used:
Total Work = Efficiency Total Time
Solution:

2(P + Q + R) = 5 + 4 + 3
P + Q + R = = 6
Efficiency of P + Q + R = 6
So, efficiency of P, Q , R:
P = 2 , Q = 3 , R = 1
Then,

Since Efficiency is double to removing the fraction, So Total work also be double:
Total Work = 450 2 = 900
Efficiency of (X + Y + Z) = 29
The number of days required to complete the same job if X, Y and Z work together.
Required Time = days or Days
Thus, the correct option is (a)