Correct option is B
Match the LIST-I with LIST-II.
List – I (Life Cycle Model) | List – II (Description) | ||
A. | Waterfall Model | I. | Interactive collaboration, customer feedback, rapid releases |
B. | Agile Methodology | II. | Automatic testing, frequent integration, main branch |
C. | Test-driven Development (TDD) | III. | Sequential, fixed steps from requirement to maintenance |
D. | Continual Integration (CI) | IV. | Write tests before code implementation |
Choose the correct answer from the options given below:
Arrange the following in the increasing order of coupling from lowest coupling to highest coupling:
A. Common Coupling
B. Stamp Coupling
C. Control Coupling
D. External Coupling
E. Content Coupling
Choose the correct answer from the options given below:
A Company has a choice of two languages and to develop a software for their client. Number of LOC required to develop an application in is thrice the LC in language . Also, software has to be maintained for next 10 years. Various parameters for two languages are given below to decide which language should be preferred for development.
PARAMETER | | |
Man-year needed for development | LOC/1000 | LOC/1000 |
Development cost | Rs. 70,000 | Rs. 90,000 |
Cost of Maintenance per year | Rs. 1,00,000 | Rs. 40,000 |
Total cost of project include cost of development and maintenance. What is the LOC for for which cost of developing the software with both languages must be same?
A Software project was estimated at 864 Function Points. A six-person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is ₹70,000 per month, requirement gatherer is ₹50,000 per month, programmer is ₹60,000 per month and a tester is ₹60,000 per month. The average productivity for the team is 12 FP per person month. Which of the following represents the projected cost of the project?
Suggested Test Series
Suggested Test Series
Match the LIST-I with LIST-II.
List – I (Life Cycle Model) | List – II (Description) | ||
A. | Waterfall Model | I. | Interactive collaboration, customer feedback, rapid releases |
B. | Agile Methodology | II. | Automatic testing, frequent integration, main branch |
C. | Test-driven Development (TDD) | III. | Sequential, fixed steps from requirement to maintenance |
D. | Continual Integration (CI) | IV. | Write tests before code implementation |
Choose the correct answer from the options given below:
Arrange the following in the increasing order of coupling from lowest coupling to highest coupling:
A. Common Coupling
B. Stamp Coupling
C. Control Coupling
D. External Coupling
E. Content Coupling
Choose the correct answer from the options given below:
A Company has a choice of two languages and to develop a software for their client. Number of LOC required to develop an application in is thrice the LC in language . Also, software has to be maintained for next 10 years. Various parameters for two languages are given below to decide which language should be preferred for development.
PARAMETER | | |
Man-year needed for development | LOC/1000 | LOC/1000 |
Development cost | Rs. 70,000 | Rs. 90,000 |
Cost of Maintenance per year | Rs. 1,00,000 | Rs. 40,000 |
Total cost of project include cost of development and maintenance. What is the LOC for for which cost of developing the software with both languages must be same?
A Software project was estimated at 864 Function Points. A six-person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is ₹70,000 per month, requirement gatherer is ₹50,000 per month, programmer is ₹60,000 per month and a tester is ₹60,000 per month. The average productivity for the team is 12 FP per person month. Which of the following represents the projected cost of the project?