Correct option is B
Let's go through the given details and calculation correctly based on the data:
1. Function Points (FP) = 864
2. Team members = 6 (1 requirement gatherer, 1 designer, 2 programmers, 2 testers)
3. Average productivity per person = 12 FP/person-month
4. Salaries:
o Designer = ₹70,000/month
o Programmer = ₹60,000/month (each)
o Tester = ₹60,000/month (each)
o Requirement Gatherer = ₹50,000/month
Step 1: Calculate the total number of months required for the project
To calculate the total number of person-months required for the project, we use the formula:
Total number of months=Team size×Average productivity per personFunctional Points (FP)
Substituting the values:
Total number of months=6×12864=12months
Step 2: Calculate the total cost of the project
The total cost of the project is determined by the monthly salaries of all team members, multiplied by the total number of months (12 months).
Total project cost=(Designer salary+2×Programmer salary+2×Tester salary+Requirement gatherer salary)×12
Substituting the values:
Total project cost=(70,000+2×60,000+2×60,000+50,000)×12
Total project cost=(70,000+120,000+120,000+50,000)×12
Total project cost=360,000×12=43,20,000
Hence, the projected cost of the project is ₹43,20,000.