Arrange the steps of the project life cycle in sequence: A. Formation of project B. Implementation C. Identification of idea D. Comple
Question



Arrange the steps of the project life cycle in sequence:
A. Formation of project
B. Implementation
C. Identification of idea
D. Completion and operation
E. Feasibility analysis and finalization
Choose the correct answer from the options given below:

A.

A, C, D, E, B

B.

C, A, E, B, D

C.

B, A, E, C, D

D.

D, C, A, B, E

Correct option is B


The correct sequence of steps in the project life cycle is as follows:
1. C. Identification of idea: This is the first step where the project idea or concept is identified. It involves recognizing a need or opportunity that can be addressed through a project.
2. A. Formation of project: After identifying the idea, the project is formed, including organizing resources, setting goals, and defining the project scope.
3. E. Feasibility analysis and finalization: This stage involves assessing the feasibility of the project, including technical, financial, and operational aspects. The final decision is made on whether to proceed with the project.
4. B. Implementation: Once the project has been finalized and planned, the implementation phase begins, where the actual work and activities are carried out to achieve the project objectives.
5. D. Completion and operation: The final stage involves completing the project, delivering the outputs, and ensuring that it operates effectively and is maintained.
Information Booster:
· Identification of Idea (C): This is the conceptualization phase where the idea is recognized, and the goals and objectives are set.
· Formation of Project (A): This stage involves setting up the necessary structures and systems to support the project.
· Feasibility Analysis and Finalization (E): This step ensures that the project is practical, cost-effective, and technically feasible before moving to the execution phase.
· Implementation (B): This is the phase where resources are allocated, tasks are completed, and milestones are met in line with the project objectives.
· Completion and Operation (D): This final stage ensures that the project is fully completed, and operations are stable for long-term sustainability.

Free Tests

Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Mock Test 1

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘UGC NET Home Science’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow