A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 5 days. In how many days can A and B togeth
Question

A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 5 days. In how many days can A and B together finish the work?

A.

45 days

B.

40 days

C.

15 days

D.

24 days

Correct option is C

Given:

A can complete the work in 24 days.

A works for 21 days.

B completes the remaining work in 5 days.

Formula Used:

Work done = Time × Efficiency

Solution:

Let the efficiencies of A and B be  A units/day and B units/day respectively.

Total work  = A×24=A×21+B×5A \times 24 = A \times 21 + B \times 5​​

3A = 5B

AB=53\frac{A}{B} = \frac{5}{3}​​

Total work = 24A = 24×524 \times 5​ = 120 units

A and B together finish the work in:

120A+B\frac{120}{A + B}​ = 1208 \frac{120}{8}​ = 15 days

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow