A, B and C together can do a piece of work in 14 days, whereas C alone can do the same work in 42 days. How long will A and B together take to finish
Question

A, B and C together can do a piece of work in 14 days, whereas C alone can do the same work in 42 days. How long will A and B together take to finish it?

A.

28 days

B.

35 days

C.

21 days

D.

7 days

Correct option is C

Given:

A, B, and C together can complete the work in 14 days

C alone can complete the work in 42 days

Formula Used:

Work per day = 1Number of days \frac{1}{\text{Number of days}} ​​

Solution:

A + B + C's 1 day work = 114\frac{1}{14}​​

C's 1 day work = 142\frac{1}{42}​​

Then,

A + B = 114142 \frac{1}{14} - \frac{1}{42}​​

=3142= \frac{3 - 1}{42}​​

=242= \frac{2}{42}​​

=121= \frac{1}{21}​​

So, A and B together can complete the work in 21 days.

Alternate Solution:  

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow