Correct option is C
Given:
A, B, and C together complete the work in 8 days
A alone = 20 days
B alone = 20 days
Find time taken by C alone
Concept Used:
Work rate =Time1
Solution:
Work = 1 unit (assumed total work)
Total work rate=81
A's rate =201,
B's rate =201
C1=81−(201+201)
C1=81−202=81−101=405−4=401
C alone can do the work in 40 days
Alternate Method:
Efficiency of C = 5 - 2 - 2 =1
Time taken by C = 140=40 days