Correct option is A
Given:
A can complete the work in 6 days
B can complete the work in 12 days
C can complete the work in 24 days
Required: Time taken by A, B, and C together to complete the work
Formula Used:
Work per day =A1+B1+C1
Time to complete work =Work per day1
Solution:
Combined work per day =61+121+241=244+2+1=247
Time = 2471=373 days
Alternate Method:
Required Time = 724=373