A and B together can complete a piece of work in 25 days, B and C together can complete the same piece of work in 36 days, while C and A together can
Question

A and B together can complete a piece of work in 25 days, B and C together can complete the same piece of work in 36 days, while C and A together can complete it in 30 days. If A, B, C, and D together can complete this piece of work in 18 days, then in how many days can D alone complete this piece of work?

A.

210

B.

180

C.

200

D.

225

Correct option is C

Given:

A and B together can complete the work in 25 days.

B and C together can complete the work in 36 days.

C and A together can complete the work in 30 days.

A, B, C, and D together can complete the work in 18 days.

Solution:

Work rate of A + B =125= \frac{1}{25}​​

Work rate of B + C =136= \frac{1}{36}​​

Work rate of C + A =130 \frac{1}{30}​​

Work rate of A + B + C + D =118 \frac{1}{18}​​

Now, 

(A + B) + (B + C) + (C + A) =125+136+130 \frac{1}{25} + \frac{1}{36} + \frac{1}{30}

2A + 2B + 2C =125+136+130 \frac{1}{25} + \frac{1}{36} + \frac{1}{30}​​

2(A + B + C) =721800+501800+601800=1821800 \frac{72}{1800} + \frac{50}{1800} + \frac{60}{1800} = \frac{182}{1800}

A+B+C=12×1821800=911800A + B + C= \frac{1}{2} \times \frac{182}{1800} = \frac{91}{1800}........(1)

A + B + C + D =118= \frac{1}{18}........(2) 

Subtracting (1) and (2), we get

D =118911800 \frac{1}{18} - \frac{91}{1800}

D = 1001800911800=91800=1200\frac{100}{1800} - \frac{91}{1800} = \frac{9}{1800} = \frac{1}{200}

The rate of work of D is 1200\frac{1}{200}​, meaning D can complete the work in 200 days.

Alternate Method:

​Efficiency of A + B + C =36+25+302=912=45.5\frac{36+25+30}2=\frac{91}2=45.5

​​Efficiency of D = 50 - 45.5 = 4.5

Work done by D =9004.5=200\frac{900}{4.5}=200 days​

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC CPO Tier I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow