Correct option is B
Given:
A + B can do the work in 4 hours → A1+B1=41
B + C can do the work in 6 hours → B1+C1=61
A + C can do the work in 8 hours →A1+C1=81
Solution:
A1+B1=41 ...(1)
B1+C1=61 .....(2)
Add equations (1) and (2):
(A1+2⋅B1+C1)=41+61=125
A1+C1=81 ....(3)
Now subtract (3) from the above sum:
(A1+2⋅B1+C1)−(A1+C1)=125−81
B2=2410−3=247
Now substitute into (2):
487+C1=61
C1=61−487=488−7=481
C alone can do the work in 48 hours
Alternate Method:
Efficiency
(A + B) + (B + C) + (A + C) = 6 + 4 + 3 = 13
A + B + C =213= 6.5 units/hour
Now subtract:
(A + B + C) – (A + B) = 6.5 – 6 = 0.5 → C = 0.5 units/hour
Time taken by C alone =0.5 units/hour24 units=48 hours