Correct option is D
Given:
3 men and 3 boys can complete the work in 10 days.
When 1 man is replaced by a boy (i.e., 2 men and 4 boys), the work is completed in 12 days.
We need to determine how many days 2 men and 2 boys will take to complete the work.
Concept Used:
The Work Formula based on the principle:
where:
represent the number of workers and days for the first scenario.
represent the number of workers and days for the second scenario.
Solution:
Let the total work be LCM of 10 and 12, i.e., 60 units.
Work done per day by (3 men + 3 boys)
Work done per day by (2 men + 4 boys)
Let the work done by 1 man per day be M and the work done by 1 boy per day be B.
From the given information:
From Equation 1 & 2:
M + B = 2; 2M + 4B = 5 => M + 2B = 2.5
Solving above equations:
B=0.5 & M=1.5
Work Done by 2 Men and 2 Boys
Since, Total work = 60 units, Days required =
Option (D) is days.
Alternate Method:
Concept Used:
(M1+B1)D1= (M2+B2)D2
where:
M1, B1 & D1 represent the number of men , boys and days for the first scenario.
M2,B2& D2 represent the number of men , boys and days for the second scenario.
Solution:
(3M + 3B )10 = (2M + 4B)12
5M + 5B=4M + 8B
M = 3B
Total work = = 120
Then,
work done per day =2M + 2B =
Days required =
Option (D) is days.