arrow
arrow
arrow
​3 men and 3 boys can do a piece of work in 10 days. When one man is replaced by a boy, the work is completed in 12 days. In how many days will 2 men
Question

3 men and 3 boys can do a piece of work in 10 days. When one man is replaced by a boy, the work is completed in 12 days. In how many days will 2 men and 2 boys complete the work?

A.

22 days

B.

20 days

C.

25 days

D.

15 days

Correct option is D

Given:

3 men and 3 boys can complete the work in 10 days.

When 1 man is replaced by a boy (i.e., 2 men and 4 boys), the work is completed in 12 days.

We need to determine how many days 2 men and 2 boys will take to complete the work.

Concept Used:

The Work Formula based on the M1D1W1=M2D2W2M_1 D_1 W_1 = M_2 D_2 W_2​ principle:

M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2​​

where:

M1,D1M_1, D_1​​ represent the number of workers and days for the first scenario.

M2,D2M_2, D_2​​ represent the number of workers and days for the second scenario.

Solution:

Let the total work be LCM of 10 and 12, i.e., 60 units.

Work done per day by (3 men + 3 boys)

6010=6(units per day)\frac{60}{10} = 6 \quad \text{(units per day)}​​

Work done per day by (2 men + 4 boys)

6012=5(units per day)\frac{60}{12} = 5 \quad \text{(units per day)}​​

Let the work done by 1 man per day be M and the work done by 1 boy per day be B.

From the given information:

3M+3B=6(Equation 1)3M + 3B = 6 \quad \text{(Equation 1)}​​

2M+4B=5(Equation 2)2M + 4B = 5 \quad \text{(Equation 2)}​​

From Equation 1 & 2:

M + B = 2; 2M + 4B = 5 => M + 2B = 2.5

Solving above equations:

B=0.5 & M=1.5

Work Done by 2 Men and 2 Boys

Work done per day=2M+2B=2(1.5)+2(0.5)=3+1=4(units per day)\text{Work done per day} = 2M + 2B = 2(1.5) + 2(0.5) =3+1=4(\text{units per day})

Since, Total work = 60 units,     Days required = 604=15 days\frac{60}{4} = 15 \text{ days}

Option (D) is days.

Alternate Method:

Concept Used:

(M1+B1)D1= (M2+B2)D2

where:

M1, B1 & D1 represent the number of men , boys and days for the first scenario.

​M2,B2& Drepresent the number of men , boys and days for the second scenario.

Solution:

(3M + 3B )10 = (2M + 4B)12

5M + 5B=4M + 8B

M = 3B 

MB=31\frac{M}{B}=\frac{3}{1}

Total work = (3×3+3×1)10(3\times 3 +3\times 1) 10 = 120

Then, 

work done per day =2M + 2B = 2×3+2×1=82 \times 3+ 2 \times1 = 8 

Days required = 1208=15\frac{120}{8}=15

​​Option (D) is days.


Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow