hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    ​3 men and 3 boys can do a piece of work in 10 days. When one man is replaced by a boy, the work is completed in 12 days. In how many days will 2 men
    Question

    3 men and 3 boys can do a piece of work in 10 days. When one man is replaced by a boy, the work is completed in 12 days. In how many days will 2 men and 2 boys complete the work?

    A.

    22 days

    B.

    20 days

    C.

    25 days

    D.

    15 days

    Correct option is D

    Given:

    3 men and 3 boys can complete the work in 10 days.

    When 1 man is replaced by a boy (i.e., 2 men and 4 boys), the work is completed in 12 days.

    We need to determine how many days 2 men and 2 boys will take to complete the work.

    Concept Used:

    The Work Formula based on the M1D1W1=M2D2W2M_1 D_1 W_1 = M_2 D_2 W_2​ principle:

    M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2​​

    where:

    M1,D1M_1, D_1​​ represent the number of workers and days for the first scenario.

    M2,D2M_2, D_2​​ represent the number of workers and days for the second scenario.

    Solution:

    Let the total work be LCM of 10 and 12, i.e., 60 units.

    Work done per day by (3 men + 3 boys)

    6010=6(units per day)\frac{60}{10} = 6 \quad \text{(units per day)}​​

    Work done per day by (2 men + 4 boys)

    6012=5(units per day)\frac{60}{12} = 5 \quad \text{(units per day)}​​

    Let the work done by 1 man per day be M and the work done by 1 boy per day be B.

    From the given information:

    3M+3B=6(Equation 1)3M + 3B = 6 \quad \text{(Equation 1)}​​

    2M+4B=5(Equation 2)2M + 4B = 5 \quad \text{(Equation 2)}​​

    From Equation 1 & 2:

    M + B = 2; 2M + 4B = 5 => M + 2B = 2.5

    Solving above equations:

    B=0.5 & M=1.5

    Work Done by 2 Men and 2 Boys

    Work done per day=2M+2B=2(1.5)+2(0.5)=3+1=4(units per day)\text{Work done per day} = 2M + 2B = 2(1.5) + 2(0.5) =3+1=4(\text{units per day})

    Since, Total work = 60 units,     Days required = 604=15 days\frac{60}{4} = 15 \text{ days}

    Option (D) is days.

    Alternate Method:

    Concept Used:

    (M1+B1)D1= (M2+B2)D2

    where:

    M1, B1 & D1 represent the number of men , boys and days for the first scenario.

    ​M2,B2& Drepresent the number of men , boys and days for the second scenario.

    Solution:

    (3M + 3B )10 = (2M + 4B)12

    5M + 5B=4M + 8B

    M = 3B 

    MB=31\frac{M}{B}=\frac{3}{1}

    Total work = (3×3+3×1)10(3\times 3 +3\times 1) 10 = 120

    Then, 

    work done per day =2M + 2B = 2×3+2×1=82 \times 3+ 2 \times1 = 8 

    Days required = 1208=15\frac{120}{8}=15

    ​​Option (D) is days.


    Free Tests

    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB Group D Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    398k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow