Correct option is C
Given:
• X and Y together can complete the work in 60 days.
• They worked together for 30 days.
• Y completed the remaining work in 75 days.
Concept Used:
Let the total work be (W), and the efficiencies of X and Y be (EX andEY respectively.
Work done by any person is calculated as:
Work = Efficiency×Time
Given that (EX+EY)=601, since they can together complete the work in 60 days.
Solution:
Work done by X and Y together in 30 days:
Worktogether=(EX+EY)×30=6030=21
Thus, half of the work is completed in 30 days.
Remaining work:
Remaining Work = 1−21=21
Work completed by Y in 75 days:
EY×75=21
Thus, EY=7521=1501.
Efficiency of X:
From EX+EY=601,
EX=601−EY=601−1501
Taking LCM: EX=3005−2=3003=1001
Time taken by X alone to complete the work:
Time = EfficiencyWork=EX1=10011=100
X alone can complete the entire work in 100 days.