    Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following?
    Question

    Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following?

    A.

    Cost per square metre method

    B.

    Cost per linear metre method

    C.

    Base unit method

    D.

    Cost per function method

    Correct option is B


    Cost per Linear Metre Method:
    This method involves calculating the cost of construction based on the linear measurement of the perimeter works, such as fencing, boundary walls, or other linear structures.
    It is particularly suited for works where the cost depends on the length of the structure.
    Purpose:
    Used for quick and approximate estimates for perimeter-related works.
    It provides an accurate basis when the linear extent of the structure (e.g., walls, railings) is the determining factor for cost calculation.

    test-prime-package

    Access ‘RRB JE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RRB JE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow