arrow
arrow
arrow
When the quantities of the work items are difficult to be quantified and the rate analysis is also a complex issue, but still the contractor is willin
Question

When the quantities of the work items are difficult to be quantified and the rate analysis is also a complex issue, but still the contractor is willing to undertake a work, then the type of Contract best suited is:

A.

Turn Key Contract

B.

Labour Contract

C.

Lump Sum Contract

D.

Item Rate Contract

Correct option is C


In a Lump Sum Contract, the contractor agrees to complete the entire project for a fixed total cost.
It is suitable when:
Quantities of work items are difficult to quantify accurately.
Rate analysis is complex.
Both parties agree on a lump sum payment, avoiding detailed measurements for payments.
Why Lump Sum Contract is Preferred in This Case:
It simplifies the payment structure as the contractor undertakes the work for a predetermined price without needing to provide detailed measurements or itemized breakdowns.
It transfers the risk of cost variations to the contractor.

test-prime-package

Access ‘RRB JE Civil Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘RRB JE Civil Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow