    When (h) is the difference in heights between the extremities of a chain length (l) then the correction for the slope required is-
    Question

    When (h) is the difference in heights between the extremities of a chain length (l) then the correction for the slope required is-

    A.

    h/l

    B.

    h²/6

    C.

    h²/2l

    D.

    h/20

    Correct option is C


    The correction for the slope in chain surveying is used to account for the difference in height between the two ends of a chain length.
    The formula for the slope correction
    When surveying over a sloped ground, the measured horizontal distance is affected by the slope. To obtain the correct horizontal distance, we need to apply a correction for the slope.

    test-prime-package

    Access ‘RPSC AE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    345k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RPSC AE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    345k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow