Correct option is B
Total precipitation = 150 mm = 15 cm
Infiltration in soil = 5 cm
Direct evaporation = 10 mm = 1 cm
Rainfall excess = Total precipitation - All losses
Rainfall excess = 15 - 5 - 1 = 9 cm
Rainfall excess = 90 mm
Total precipitation = 150 mm = 15 cm
Infiltration in soil = 5 cm
Direct evaporation = 10 mm = 1 cm
Rainfall excess = Total precipitation - All losses
Rainfall excess = 15 - 5 - 1 = 9 cm
Rainfall excess = 90 mm