arrow
arrow
arrow
What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?
Question

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

A.

Interfering float

B.

Independent float

C.

Free float

D.

Total float

Correct option is C


The free float is defined as the amount of time by which the completion of an activity can be delayed without affecting the start of any succeeding activities. It is a type of float specific to an individual activity and does not influence the float of succeeding activities.
Key Definitions:
Interfering Float: The portion of total float that affects succeeding activities.
Independent Float: The amount of time an activity can be delayed without affecting either its preceding or succeeding activities.
Free Float: The amount of time an activity can be delayed without delaying the start of any succeeding activities.
Total Float: The total amount of time an activity can be delayed without delaying the overall project duration.

Similar Questions

test-prime-package

Access ‘RSMSSB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘RSMSSB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow