hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?
    Question

    What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

    A.

    Interfering float

    B.

    Independent float

    C.

    Free float

    D.

    Total float

    Correct option is C


    The free float is defined as the amount of time by which the completion of an activity can be delayed without affecting the start of any succeeding activities. It is a type of float specific to an individual activity and does not influence the float of succeeding activities.
    Key Definitions:
    Interfering Float: The portion of total float that affects succeeding activities.
    Independent Float: The amount of time an activity can be delayed without affecting either its preceding or succeeding activities.
    Free Float: The amount of time an activity can be delayed without delaying the start of any succeeding activities.
    Total Float: The total amount of time an activity can be delayed without delaying the overall project duration.

    Similar Questions

    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow