Correct option is B
The Total Quantity Method is a type of detailed estimate. In this method, the entire quantity of each item of work (like earthwork, concrete, brickwork, etc.) is calculated from drawings and specifications, and then the cost is estimated by multiplying the quantity with the rate per unit. This method provides a highly accurate and itemized cost breakdown, typically used for preparing detailed estimates of construction projects.