arrow
arrow
arrow
The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the
Question

The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in _____ days.

A.

5.5

B.

5.75

C.

5

D.

5.25

Correct option is A

Given:
A can finish the work in 12 days.
The number of days to finish the work by A is double the number of days to finish the work by B.
The number of days to finish the work by C is half the number of days to finish the work by B.
B works on the 1st day, A works on the 2nd day, and C works on the 3rd day, and this cycle repeats.
Concept Used:
We use the LCM method to find the total number of days required to finish the work when three people work alternately.
We find the work done per person per day and then calculate the total work done in one cycle (3 days)
Solution:
Since, A can finish the work in 12 days.
B finishes the work in 122=\frac{12}{2}=​ 6 days.

C finishes the work in 62=3\frac 62 =3 days.
Total Work = LCM of 12, 6 and 3 = 12 unit
Efficiency of A, B and C = 1212=1 unit per day,126=2 unit per day,123=4 unit per day\frac{12}{12} = 1\, \text{unit per day}, \frac{12}{6} = 2 \, \text{unit per day}, \frac{12}{3} = 4 \, \text{unit per day} respectively. 
As B works on first day = 2 unit of work completed
Then A works on second day = 1 unit of work completed
Then, C works on third day = 4 unit of work completed 
In 3 days, 7 unit of work completed
Remaining Work = 12-7= 5 unit  
Now, the 4th day will be completed by B = 2 unit of work
5th day work will be done by A = 1 unit of work 
Remaining 2 unit of work will be completed by C in = 24=0.5\frac{2}{4} = 0.5  days
Total Time Taken to complete the whole work  = 5+ 0.5 = 5.5 days



Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow