hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the
    Question

    The number of days to finish a work by A is double the number of days to finish the work by B. The number of days to finish the work by C is half the number of days to finish the work by B. A can finish the work in 12 days. If B works on the 1st day, A works on the 2nd day and C works on the 3rd day, again B works on the 4th day and so on, then the work is finished in _____ days.

    A.

    5.5

    B.

    5.75

    C.

    5

    D.

    5.25

    Correct option is A

    Given:
    A can finish the work in 12 days.
    The number of days to finish the work by A is double the number of days to finish the work by B.
    The number of days to finish the work by C is half the number of days to finish the work by B.
    B works on the 1st day, A works on the 2nd day, and C works on the 3rd day, and this cycle repeats.
    Concept Used:
    We use the LCM method to find the total number of days required to finish the work when three people work alternately.
    We find the work done per person per day and then calculate the total work done in one cycle (3 days)
    Solution:
    Since, A can finish the work in 12 days.
    B finishes the work in 122=\frac{12}{2}=​ 6 days.

    C finishes the work in 62=3\frac 62 =3 days.
    Total Work = LCM of 12, 6 and 3 = 12 unit
    Efficiency of A, B and C = 1212=1 unit per day,126=2 unit per day,123=4 unit per day\frac{12}{12} = 1\, \text{unit per day}, \frac{12}{6} = 2 \, \text{unit per day}, \frac{12}{3} = 4 \, \text{unit per day} respectively. 
    As B works on first day = 2 unit of work completed
    Then A works on second day = 1 unit of work completed
    Then, C works on third day = 4 unit of work completed 
    In 3 days, 7 unit of work completed
    Remaining Work = 12-7= 5 unit  
    Now, the 4th day will be completed by B = 2 unit of work
    5th day work will be done by A = 1 unit of work 
    Remaining 2 unit of work will be completed by C in = 24=0.5\frac{2}{4} = 0.5  days
    Total Time Taken to complete the whole work  = 5+ 0.5 = 5.5 days



    test-prime-package

    Access ‘SSC GD’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    166k+ students have already unlocked exclusive benefits with Test Prime!

    Free Tests

    Free
    Must Attempt

    SSC CPO T-I PYP (Held on 27 June 2024 S1)

    languageIcon English
    • pdpQsnIcon200 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon120 Mins
    languageIcon English
    Free
    Must Attempt

    English Comprehension Section Test 01

    languageIcon English
    • pdpQsnIcon50 Questions
    • pdpsheetsIcon50 Marks
    • timerIcon20 Mins
    languageIcon English
    Free
    Must Attempt

    SSC JHT 2025 Mini Mock 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon60 Mins
    languageIcon English