Correct option is A
Given:
P can complete the work in 28 days, so A’s work per day =
Q can complete the work in 35 days, so B’s work per day =
P starts the work and they work on alternate days.
Solution:
Work done in 2 days ==
In 2 days, work done =
how many full cycles are needed
15 ×
So, after 15 full cycles (30 days)
Remaining work: 1 -
P works on the 31th day
A’s work per day, Hence, Remaining work is also same.
So, Total 31 days to complete the work
Alternate Method:

Total Work = 140 Unit
Work Done in 2 Days = 4 + 5 = 9
15 9 = 135 Unit
So, after 15 full cycles (30 days)
Remaining work = 140 - 135 = 5 Unit
P works on the 31th day, Remaining 5 unit of work, should be completed by P on that day
Total time = 30+1 = 31 days