    The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:
    Question

    The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:

    A.

    output indices

    B.

    input indices

    C.

    seller’s indices

    D.

    relational indices

    Correct option is B


    Input indices - The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called input indices.

    Similar Questions

    test-prime-package

    Access ‘SSC JE Civil’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    353k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘SSC JE Civil’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    353k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow