The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:
Question
The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:
A.
output indices
B.
input indices
C.
seller’s indices
D.
relational indices
Correct option is B
Input indices - The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called input indices.