The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:
Question

The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called as:

A.

output indices

B.

input indices

C.

seller’s indices

D.

relational indices

Correct option is B


Input indices - The method that measures changes in the price of inputs to the construction process by monitoring separately the cost of each factor is called input indices.

Similar Questions

test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow