Correct option is C
Given:
P's time to complete the work = 10 days
Q's time to complete the work = 24 days
Together with R, they complete the work in 6 days
Total remuneration = Rs. 1000
Formula Used:
The amount of work done per day by each person is the reciprocal of the number of days they take to complete the work.
Work done by P per day = 1/10
Work done by Q per day = 1/24
Let R's work done per day be 1/x.
Total work done per day by P, Q, and R together = 1/6.
Solution:
Set up the equation for their combined work
.
So, R takes 40 days to complete the work alone.
the total work done by each person in 6 days.
P's work = (1/10) × 6 = 0.6
Q's work = (1/24) × 6 = 0.25
R's work = (1/40) × 6 = 0.15
the payments based on the work done.
Total work done = 0.6 + 0.25 + 0.15 = 1
P's share of the payment = 0.6 × 1000 = Rs.600
Q's share of the payment = 0.25 × 1000 = Rs.250
R's share of the payment = 0.15 × 1000 = Rs.150
P receives Rs.600, Q receives Rs.250, and R receives Rs.150.