P, Q and R can do a work in 15, 20 and 30 days respectively. The contractor decides to put any two of them on the job so as to finish the work earlier.
Question

P, Q and R can do a work in 15, 20 and 30 days respectively. The contractor decides to put any two of them on the job so as to finish the work earlier. Which of these choices is the best?

A.

Either PQ or QR

B.

QR

C.

RP

D.

PQ

Correct option is D


Given:
P, Q and R can do a work in 15, 20 and 30 days respectively
Concept Used:
Ratio of time is inverse proportion to the efficiency
Solution:
Ratio of time of P, Q and R = 15:20:30 = 3:4:6
Efficiency of P, Q and R = 1/3, 1/4, 1/6=4:3:2
Therefore, P and Q are more than that of R.
Thus, correct option is PQ.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE CBT-I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow