arrow
arrow
arrow
P is 30% more efficient than Q. If P alone can do some work in 20 days, then how long will Q alone take to do it?
Question

P is 30% more efficient than Q. If P alone can do some work in 20 days, then how long will Q alone take to do it?

A.

30 days

B.

18 days

C.

28 days

D.

26 days

Correct option is D

Given:
P is 30% more efficient than Q. P can do the work alone in 20 days.
Formula Used:
Efficiency ratio: If P is 30% more efficient than Q, then Efficiency of P: Efficiency of Q = 130:100 = 13:10. The time taken to complete the work is inversely proportional to efficiency.
Solution:
Since P is 30% more efficient than Q, the efficiency ratio of P and Q is 13:10. The time taken by P and Q to complete the work will be in the inverse ratio of their efficiencies. Thus, the time ratio of P and Q = 10:13. If P takes 20 days to complete the work, then: Time taken by Q = (13/10) * 20 = 26 days.
Alternate Method:
Let Q can complete the work in x days
So work done by Q in one day = 1/x
Work done by P in one day = 1/20
Then x×130/100=1/20
x= 100/(20×130)
x=1/26
Therefore, Q can complete the work in 26 days.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE CBT-I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow