P and Q together can do a job in 7 days. P is twice as efficient as Q. In how many days can P alone do the job?
Question

P and Q together can do a job in 7 days. P is twice as efficient as Q. In how many days can P alone do the job?

A.

21 days

B.

12 days

C.

10.5 days

D.

15 days

Correct option is C


Let the efficiency of Q = 1 Unit/day
As per question
The efficiency of Q = 2 Unit/day
P and Q together can do a job in 7 days
Total job done by P and Q in 1 day = 2+1=3
Therefore, total work

P can do these Job = 21/2 = 10.5 days.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow