Correct option is D
Given:
P and Q together complete the work in 40 days.
Q and R together complete the work in 120 days.
Q alone completes the work in 180 days.
Formula Used:
Work done in one day=Number of days to complete the work1
Solution:
Let the total work be 1 unit.
Work done by Q in 1 day = 1801
Work done by P and Q in 1 day = 401
Work done by Q and R in 1 day = 1201
Work done by P in 1 day = 401−1801=3609−2=3607
Work done by R in 1 day = 1201−1801=3603−2=3601
Work done by P and R in 1 day = 3607+3601=3608=902
\text{Number of days required by P and R} = 9021=45
Hence, P and R together will finish the work in 45 days.