    Lag time is the

    A.

    time by which an event preceded by it must be completed.

    B.

    earliest time by which a successor event can follow a specific PERT event.

    C.

    time performing more critical activities in parallel.

    D.

    measure of the excess time & resources available.

    Correct option is B


    Lag time in project management refers to the delay or gap between two activities in a schedule. It is the minimum amount of time required before a successor event or activity can begin after a predecessor event or activity has been completed.
    In the context of PERT (Program Evaluation and Review Technique), lag time ensures proper sequencing of dependent tasks.

    Similar Questions

    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow