Question

Lag time is the

A.

time by which an event preceded by it must be completed.

B.

earliest time by which a successor event can follow a specific PERT event.

C.

time performing more critical activities in parallel.

D.

measure of the excess time & resources available.

Correct option is B


Lag time in project management refers to the delay or gap between two activities in a schedule. It is the minimum amount of time required before a successor event or activity can begin after a predecessor event or activity has been completed.
In the context of PERT (Program Evaluation and Review Technique), lag time ensures proper sequencing of dependent tasks.

Similar Questions

test-prime-package

Access ‘RSMSSB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘RSMSSB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
383k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow