Correct option is B
Lag time in project management refers to the delay or gap between two activities in a schedule. It is the minimum amount of time required before a successor event or activity can begin after a predecessor event or activity has been completed.
In the context of PERT (Program Evaluation and Review Technique), lag time ensures proper sequencing of dependent tasks.