In approximate quantity method, for superstructure, __________.
Question

In approximate quantity method, for superstructure, __________.

A.

price per running metre is determined

B.

price per cubic metre is determined

C.

price per cubic feet is determined

D.

price per square metre is determined

Correct option is A


The following are the common methods used to estimate buildings:
Plinth area or square meter method.
Cubic rate or cubic meter method.
Unit rate method or Service unit.
Bay method.
Cost comparison method.
Cost from materials and labour.
Approximate quantities with bill method.
Approximate quantities with bill method:
In this method, the structure is divided into:
(a) Foundation Inclusive of Plinth 
(b) The Super Structure.
The cost per running meter of the foundation inclusive of the plinth is worked out and is multiplied by the total length of the foundation to determine the total cost of the foundation inclusive of the plinth .
Similarly, the cost per running meter of the superstructure is found and is multiplied by the total length of all the walls of the superstructure to get the total cost of the superstructure.
The total cost of the structure is then obtained by the addition of total cost of foundation inclusive of plinth to the total cost of the superstructure.

Similar Questions

test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow