hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    Hemant and Irfan can complete a certain piece of work in 9 and 14 days, respectively, They started to work together, and after 3 days, Irfan left
    Question

    Hemant and Irfan can complete a certain piece of work in 9 and 14 days, respectively, They started to work together, and after 3 days, Irfan left. In how many days will Hemant complete the remaining work?

    A.

    17142\frac{171}{42}​​

    B.

    17344\frac{173}{44}

    C.

    17542\frac{175}{42}​​

    D.

    17043\frac{170}{43}​​

    Correct option is A

    Given:

    Hemant can complete the work in 9 days.

    Irfan can complete the work in 14 days.

    Hemant and Irfan worked together for 3 days.

    Formula Used:

    Work Done = Rate of Work × Time

    Solution:

    Hemant's rate of work is 19\frac{1}{9}​ of the work per day.

    Irfan's rate of work is 114\frac{1}{14}​ of the work per day.

    ​Work done by Hemant and Irfan together in 1 day:

    19+114\frac{1}{9} + \frac{1}{14}

    So, together, their combined rate of work is:

    14126+9126=23126\frac{14}{126} + \frac{9}{126} = \frac{23}{126}

    Work done by Hemant and Irfan together in 3 days:

    Work Done =23126×3=69126=2342 \frac{23}{126} \times 3 = \frac{69}{126} = \frac{23}{42}

    So, in 3 days, they completed 2342\frac{23}{42}​ of the work.

    The remaining work is:

    12342=42422342=19421 - \frac{23}{42} = \frac{42}{42} - \frac{23}{42} = \frac{19}{42}

    Time taken by Hemant to complete the remaining work:
    Hemant works at a rate of 19\frac{1}{9}​ per day, so the time required for him to complete the remaining 1942\frac{19}{42}​ of the work is:

    Time =194219=1942×9=17142 \frac{\frac{19}{42}}{\frac{1}{9}} = \frac{19}{42} \times 9 = \frac{171}{42}​ days

    Alternate Method:

    LCM of 9 and 14 = 126

    This means in one day, we can consider the total work as 126 parts.

    Hemant completes 1269=\frac{126}{9} =​ 14 parts per day.

    Irfan completes 12614\frac{126}{14}​ = 9 parts per day.
    Together, Hemant and Irfan complete:

    14 + 9 = 23 parts per day

    So, their combined rate of work is 23 parts per day.
    In 3 days, they will complete:

    23 × 3 = 69 parts

    The total work is 126 parts, so after 3 days, the remaining work is:

    126 − 69 = 57 parts
    Now, Hemant has to complete the remaining 57 parts. Since Hemant works at a rate of 14 parts per day,

    the time Hemant will take to complete the remaining work is:

    5714=17142days\frac{57}{14} = \frac{171}{42} \text{days}

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RPF Constable’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow