arrow
arrow
arrow
Hemant and Irfan can complete a certain piece of work in 9 and 14 days, respectively, They started to work together, and after 3 days, Irfan left
Question

Hemant and Irfan can complete a certain piece of work in 9 and 14 days, respectively, They started to work together, and after 3 days, Irfan left. In how many days will Hemant complete the remaining work?

A.

17142\frac{171}{42}​​

B.

17344\frac{173}{44}

C.

17542\frac{175}{42}​​

D.

17043\frac{170}{43}​​

Correct option is A

Given:

Hemant can complete the work in 9 days.

Irfan can complete the work in 14 days.

Hemant and Irfan worked together for 3 days.

Formula Used:

Work Done = Rate of Work × Time

Solution:

Hemant's rate of work is 19\frac{1}{9}​ of the work per day.

Irfan's rate of work is 114\frac{1}{14}​ of the work per day.

​Work done by Hemant and Irfan together in 1 day:

19+114\frac{1}{9} + \frac{1}{14}

So, together, their combined rate of work is:

14126+9126=23126\frac{14}{126} + \frac{9}{126} = \frac{23}{126}

Work done by Hemant and Irfan together in 3 days:

Work Done =23126×3=69126=2342 \frac{23}{126} \times 3 = \frac{69}{126} = \frac{23}{42}

So, in 3 days, they completed 2342\frac{23}{42}​ of the work.

The remaining work is:

12342=42422342=19421 - \frac{23}{42} = \frac{42}{42} - \frac{23}{42} = \frac{19}{42}

Time taken by Hemant to complete the remaining work:
Hemant works at a rate of 19\frac{1}{9}​ per day, so the time required for him to complete the remaining 1942\frac{19}{42}​ of the work is:

Time =194219=1942×9=17142 \frac{\frac{19}{42}}{\frac{1}{9}} = \frac{19}{42} \times 9 = \frac{171}{42}​ days

Alternate Method:

LCM of 9 and 14 = 126

This means in one day, we can consider the total work as 126 parts.

Hemant completes 1269=\frac{126}{9} =​ 14 parts per day.

Irfan completes 12614\frac{126}{14}​ = 9 parts per day.
Together, Hemant and Irfan complete:

14 + 9 = 23 parts per day

So, their combined rate of work is 23 parts per day.
In 3 days, they will complete:

23 × 3 = 69 parts

The total work is 126 parts, so after 3 days, the remaining work is:

126 − 69 = 57 parts
Now, Hemant has to complete the remaining 57 parts. Since Hemant works at a rate of 14 parts per day,

the time Hemant will take to complete the remaining work is:

5714=17142days\frac{57}{14} = \frac{171}{42} \text{days}

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RPF Constable’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow