Correct option is A
Given:
Hemant can complete the work in 9 days.
Irfan can complete the work in 14 days.
Hemant and Irfan worked together for 3 days.
Formula Used:
Work Done = Rate of Work × Time
Solution:
Hemant's rate of work is of the work per day.
Irfan's rate of work is of the work per day.
Work done by Hemant and Irfan together in 1 day:
So, together, their combined rate of work is:
Work done by Hemant and Irfan together in 3 days:
Work Done =
So, in 3 days, they completed of the work.
The remaining work is:
Time taken by Hemant to complete the remaining work:
Hemant works at a rate of per day, so the time required for him to complete the remaining of the work is:
Time = days
Alternate Method:
LCM of 9 and 14 = 126
This means in one day, we can consider the total work as 126 parts.
Hemant completes 14 parts per day.
Irfan completes = 9 parts per day.
Together, Hemant and Irfan complete:
14 + 9 = 23 parts per day
So, their combined rate of work is 23 parts per day.
In 3 days, they will complete:
23 × 3 = 69 parts
The total work is 126 parts, so after 3 days, the remaining work is:
126 − 69 = 57 parts
Now, Hemant has to complete the remaining 57 parts. Since Hemant works at a rate of 14 parts per day,
the time Hemant will take to complete the remaining work is: