    Give the full form of CPM :
    Question

    Give the full form of CPM :

    A.

    Construction Project Manager

    B.

    Construction Protocol Management

    C.

    Contractor Project Management

    D.

    Critical Path Method

    Correct option is D


    CPM (Critical Path Method) is a project management technique used to plan, schedule, and control complex projects. It identifies the sequence of critical activities that determine the minimum project duration. It is widely used in construction, engineering, and other industries to ensure efficient project completion.

    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    446k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RSMSSB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    446k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow