Correct option is B
Given:
Ajay can do the work in 21 days.
Bablu can do the work in 28 days.
Chirag can do the work in 15 days.
Ajay and Chirag work for the first 5 days; then Bablu joins till completion.
Solution:
Let x be Bablu’s working days after day 5.
Rates: A=211;B=281;C=151
Work equation:
5(A+C)+x(A+B+C)=1.
A+C=211+151=10512=354,
A+B+C=211+281+151=203.
So
5×354+x×203=1 3520+x⋅203=1 74+x⋅203=1 x⋅203=1−74=73 x=73×320=720 days.
So, Bablu worked 276 days.
Alternate Method:
Work–rate method with total work = LCM(21,28,15)=420 units.
Daily rates: A=21420=20,B=28420=15,C=15420=28units/day.
First 5 days by Ajay & Chirag: rate = 20 + 28 = 48 units/day.
Work done =5×48=240units.
Remaining work = 420 - 240 = 180 units.
With all three: rate = 20 + 15 + 28 = 63 units/day.
Time to finish =63180=720days =276days.
So, Bablu worked 276 days.