Correct option is B
Given:
Time taken by 1 man to complete the work = 20 days
Time taken by 1 woman to complete the work = 45 days
Number of men = 2
Number of women = 3
Formula Used:
Work Rate =
Total Work Rate = (Number of men × Man’s rate) + (Number of women × Woman’s rate)
Time =
Solution:
Work rate of 1 man =
Work rate of 1 woman =
Combined rate of 2 men and 3 women = 2 × + 3 ×
=
=
Time to complete the work = = 6 days
Alternate Method:
Formula Used:
Efficiency
Total Efficiency = (Men's efficiency × No. of men) + (Women's efficiency × No. of women)
Solution:
Assume total work = LCM of 20 and 45 = 180 units
Efficiency of 1 man = = 9 units/day
Efficiency of 1 woman = = 4 units/day
Total efficiency of 2 men and 3 women = (2 × 9) + (3 × 4) = 18 + 12 = 30 units/day
Time = 180 ÷ 30 = 6 days