Correct option is B
Given:
A man can complete the task in 7 days.
With the help of his son, they can complete the task in 4 days.
We need to find how many days the son alone can complete the task.
Solution:
Work rate of man =
Combined work rate =
The combined work rate is the sum of the individual work rates of the man and his son:
Combined work rate = Work rate of man + Work rate of son
Let the time taken by the son be x. Thus, we have:
= 9 days
The son can complete the task alone in days.
Alternate Method:

Efficiency of Son = 7 - 4 = 3
Son complete the work = days