A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task
Question
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?