A can lay a railway track between two given stations in 8 days and B can do the same job in 24 days. With the help of C, they can do the job in 3
Question

A can lay a railway track between two given stations in 8 days and B can do the same job in 24 days. With the help of C, they can do the job in 3 days. C alone can do the job in:

A.

7 days

B.

8 days

C.

6 days

D.

9 days

Correct option is C

Given:

A completes the job in 8 days, B in 24 days, and (A + B + C) together in 3 days.

Find C’s time alone.

Formula Used:
Work rate =1time.= \frac{1}{\text{time}} .​​
Solution:

A’s rate =18= \frac{1}{8}​, B’s rate =124 \frac{1}{24}​​

A + B rate =18+124=16 \frac{1}{8} + \frac{1}{24} = \frac{1}{6}​.

(A + B + C) rate = 13\frac{1}{3}​​
So,

16+1C=13 1C=1316=16 \frac{1}{6} + \frac{1}{C} = \frac{1}{3} \\ \ \\\frac{1}{C} = \frac{1}{3} - \frac{1}{6} = \frac{1}{6}​​
Hence C = 6 days.

Alternate Method—
Assume total work = LCM(8,24) = 24 units.
In 1 day: A does 3 units, B does 1 unit.
Together with C they finish in 3 days → per day = 24/3 = 8 units.
Thus C per day = 8 - (3 + 1) = 4 units

time = 24/4 = 6 days.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow