hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    A and B together can finish a task in 12 days. B and C together can finish it in 18 days. If A is three times more efficient than C, then in what time
    Question

    A and B together can finish a task in 12 days. B and C together can finish it in 18 days. If A is three times more efficient than C, then in what time B alone would finish the same task?

    A.

    22 days

    B.

    25 days

    C.

    24 days

    D.

    20 days

    Correct option is C

    Given:

    A + B can complete the work in 12 days

    B + C can complete the work in 18 days

    A is three times more efficient than C → i.e., A = 3C

    Formula Used:

    Work = Efficiency × Time

    Solution:

    Let total work = LCM of 12 and 18 = 36 units

    A + B efficiency =3612= \frac{36}{12} =​ 3 units/day

    B + C efficiency =3618 \frac{36}{18} ​= 2 units/day

    Let C’s efficiency = x, then A = 3x

    From the equations:

    A + B = 3

    3x + B = 3

    B = 3 - 3x

    B + C = 2

    B + x = 2

    Substitute B from above:

    3 - 3x + x = 2

    3 - 2x = 2

    x =12 \frac{1}{2}

    Then,
    B = 3 - 3x = 332=32 - \frac{3}{2} = \frac{3}{2}​ units/day

    Time taken by B alone =

    3632=36×23=24 days\frac{36}{\frac{3}{2}} = 36 \times \frac{2}{3} = 24 \text{ days}

    Alternate Method:

    Let efficiencies (work per day)
    Let C’s efficiency = x units/day.
    Then, A’s efficiency = 3x units/day (since A is 3 times more efficient than C).
    Let B’s efficiency = y  units/day.
    A + B finish work in 12 days:
    (3x + y)×12=Total Work(Equation 1) \times 12 = \text{Total Work} \quad \text{(Equation 1)}​​
    B + C finish work in 18 days:
    (y+x)×18=(y + x) \times 18 =Total Work(Equation 2) \text{Total Work} \quad \text{(Equation 2)}​​
    (3x+y)×12=(y+x)×18(3x + y) \times 12 = (y + x) \times 18​​
    36x + 12y = 18y + 18x
    36x - 18x = 18y - 12y
    18x = 6y
    y = 3x
    Substitute y = 3x into Equation 2:
    (y+x)×18=(3x+x)×18=4x×18=72x units(y + x) \times 18 = (3x + x) \times 18 = 4x \times 18 = 72x \text{ units}​​
    B’s efficiency = y = 3x  units/day.
    Time=Total WorkEfficiency=72x3x=24 days\text{Time} = \frac{\text{Total Work}}{\text{Efficiency}} = \frac{72x}{3x} = 24 \text{ days}​​

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow