Correct option is C
Given:
A + B can complete the work in 12 days
B + C can complete the work in 18 days
A is three times more efficient than C → i.e., A = 3C
Formula Used:
Work = Efficiency × Time
Solution:
Let total work = LCM of 12 and 18 = 36 units
A + B efficiency = 3 units/day
B + C efficiency == 2 units/day
Let C’s efficiency = x, then A = 3x
From the equations:
A + B = 3
3x + B = 3
B = 3 - 3x
B + C = 2
B + x = 2
Substitute B from above:
3 - 3x + x = 2
3 - 2x = 2
x =
Then,
B = 3 - 3x = 3 units/day
Time taken by B alone =
Alternate Method:
Let efficiencies (work per day)
Let C’s efficiency = x units/day.
Then, A’s efficiency = 3x units/day (since A is 3 times more efficient than C).
Let B’s efficiency = y units/day.
A + B finish work in 12 days:
(3x + y)
B + C finish work in 18 days:
36x + 12y = 18y + 18x
36x - 18x = 18y - 12y
18x = 6y
y = 3x
Substitute y = 3x into Equation 2:
B’s efficiency = y = 3x units/day.