Correct option is C
Given:
A + B can complete the work in 20 days → A + B = 1/20 work/day
B + C can complete the work in 30 days → B + C = 1/30 work/day
A + C can complete the work in 24 days → A + C = 1/24 work/day
Formula/Concept:
To find A alone's work/day:
A = (A + B + C) − (B + C)
We first calculate A + B + C by adding the three equations:
(A + B) + (B + C) + (A + C) = 2A + 2B + 2C = sum
Then divide by 2 to get A + B + C
Solution:
(A + B)’s 1 day work=201 (B + C)’s 1 day work=301 (A + C)’s 1 day work=241Now, add (A + B) and (B + C): 201+301=603+2=605=121(A + B + B + C) - (A + C) = 2B =>121−241=242−1=241 =>2B=241=>B=481Now substitute B into (A + B) = 201 A+481=201 A=201−481 =24012−5=2407So, A alone can do the work in 7240=3472 days