Correct option is A
Given:
A can complete the job in 25 days
rate = job/day.
B can complete the job in 18 days
rate job/day.
A works alone for 4 days, then leaves.
Find: Days required by B to finish the remaining work.
Formula Used:
Work done = Rate Time.
Solution:
Work done by A in 4 days
Remaining work =
Time for B to finish = = days.
Alternate Method:
Take total work = LCM(25,18)=450 units.
A’s rate =450/25=18 units/day
in 4 days does 72 units.
Remaining = 450 - 72 = 378 units.
B’s rate = 450/18 = 25 units/day
days.