    2 men can finish a work in 6 days and 3 women can finish the same work in 4 days. In how many days will the work be finished by 1 man and 2 women, wor
    Question

    2 men can finish a work in 6 days and 3 women can finish the same work in 4 days. In how many days will the work be finished by 1 man and 2 women, working together every day?

    A.

    6

    B.

    7

    C.

    8

    D.

    9

    Correct option is A

    Given:
    ​2 men can finish the work in 6 days.
    3 women can finish the work in 4 days.
    Formula Used:
    Work done = Efficiency × Time 
    Solution: 
    let the efficiency of Man be M and efficiency of woman be W.

    Thus, the time required to complete the work is 6 days.

    Free Tests

    Free
    Must Attempt

    SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I GA Section Test 01

    languageIcon English
    • pdpQsnIcon25 Questions
    • pdpsheetsIcon50 Marks
    • timerIcon15 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I Full Mock Test 1 (Exam Level)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC CGL Tier I’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow