Correct option is A
Given:
Total cost of the work = Rs. 4,480
X worked for 4 days, Y worked for 6 days, and Z worked for 8 days.
The daily salaries of X, Y, and Z are in the ratio 5 : 6 : 7.
Solution:
Let X's daily wage = 5k, Y's daily wage = 6k, Z's daily wage = 7k.
Total earnings =
Total earnings = 20k + 36k + 56k
Total earnings = 112k
Since the total payment for the work is Rs. 4,480:
112k = 4480
X's earnings = 20k =
So, X will receive Rs. 800.
Thus, the correct answer is (a).
Alternative Method:

5x : 9x : 14x
Total 28x
28x = 4480
x =
X = 5x = 5 × 160 = 800