Which of the following triggers the failure of successive parts?
Question

Which of the following triggers the failure of successive parts?

A.

Brown out

B.

Incipient fault in power transformer

C.

Load shedding

D.

Non-cascade tripping

Correct option is A

A brownout refers to a partial, temporary reduction in voltage in an electrical power supply, rather than a complete blackout.
 Brownouts can lead to the failure of electrical equipment due to insufficient voltage, which may cause devices to malfunction or operate inefficiently.
 This condition can result in overheating or excessive current draw, potentially leading to the failure of successive parts of the electrical system or connected devices.

test-prime-package

Access ‘SSC JE Electrical’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
370k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SSC JE Electrical’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
370k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow