Which of the following is the most reliable estimate?
Question

Which of the following is the most reliable estimate?

A.

Detailed estimate

B.

Plinth area estimate

C.

Cube rate estimate

D.

Preliminary estimate

Correct option is A



The detailed estimate is the most reliable estimate as it is based on the complete information about the project, including accurate measurements, specifications, and quantities of materials required. This type of estimate is prepared after the design is finalized and provides a precise cost prediction.

test-prime-package

Access ‘RRB JE Civil Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘RRB JE Civil Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow