hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    Which of the following is the input component(s) to Materials Requirement Planning (MRP) system?
    Question

    Which of the following is the input component(s) to Materials Requirement Planning (MRP) system?

    A.

    Bill of materials

    B.

    Master Production Schedule

    C.

    Inventory status file

    D.

    All of the options

    Correct option is D


    The input components to a Materials Requirement Planning (MRP) system include:
    Bill of materials (BOM): This is a detailed list of all the raw materials, components, and
    assemblies required to manufacture a product.
    Master Production Schedule (MPS): This is a plan for the production of individual end items, specifying the quantities and dates of production.
    Inventory status file: This file contains data on the inventory levels of raw materials,
    components, and finished goods.
    All these components work together in the MRP system to ensure that the right materials are available for production at the right time.

    test-prime-package

    Access ‘RRB JE Mechanical Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RRB JE Mechanical Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow