Correct option is D
Correct Answer:(d) 5,000 km
Explanation: In the Railway Budget 2018, the Indian government set a target to convert 5,000 kilometers of railway tracks to broad gauge. This initiative aimed to enhance capacity, improve connectivity, and eliminate bottlenecks in the railway network.
Key Points for Exam:
· Gauge conversion target: 5,000 km as per Railway Budget 2018.
· Objective: To upgrade existing tracks to broad gauge for improved efficiency.
Additional railway infrastructure plans:
· 18,000 km of doubling, third, and fourth line projects.
· 36,000 km of track renewal projects.
· Elimination of 4,267 unmanned level crossings on broad gauge routes within two years.
· Impact: Enhanced railway network capacity, reduced congestion, and improved safety.